School opening could be delayed
"We can't have any bad weather days." - Architect Jim Singleton
Thursday, August 17, 2006
Shiner School Construction News |
Construction Watch Home Page |
Shiner Home Page
|
The opening of the new school is scheduled for December, but it could be
Spring Break before it opens, according to architect Jim Singleton. Pictured
above is the gym's north side classroom area.
|
photo by Shiner Gazette
|
Architect Jim Singleton gave his usual monthly school building progress report
to the SISD Board at their meeting, August 9.
He said Sterling Structures is doing a good job. "They have some good crews,"
he said. "I'm pleased."
Singleton said the root' should be completed in another week and the dressing
room area should be 100 percent complete next month.
Michael Huser asked if everything was still on line for a December completion.
"We're trying for December 20," said Singleton. "But we can't have any bad
weather days or construction delays. If these occur we may run into January,
probably middle of January," he said.
He suggested that the board may have to reconsider the timing of the 'move in'
and set it for spring. Singleton said everyone is hopeful for the December
completion but wanted the board to know that there may be a delay.
Superintendent Trey Lawrence said he took some of the teaches for a walk thru
of the classrooms and everyone was pleased.
Board president, Denise Overton said she was impressed with the view from the
upper level windows. "There is no bad view from any of the upper level
windows,"' she said.
Singleton suggested that the board begin their September meeting at the new
school to get a first hand view of the complex.
The board approved this month's construction payment of $741,684.
Some of the big money items included fire pump and fire line, masonry work,
framing and sheathing and pre engineered metal buildings and fire sprinkler
system.
reprinted by permission.
The Shiner Gazette is published weekly in Shiner, Texas.
Agnes Sedlmyer, Managing Editor and Myra Lampley, News Editor
Contact them at 361-594-3346, or by e-mail at
shinergazette@sbcglobal.net.
Shiner School Construction News |
Construction Watch Home Page |
Shiner Home Page
http://www.shinertx.com/newschool/sg060817.htm
This Website brought to you by:
BaerCom
1019 N. Avenue C Shiner, Texas 77984
Phone: (361) 594-4176
E-Mail: web@shinertx.com
© Copyright
BaerCom - Shiner, Texas 2007
|